Egbert Taylor - ERP ImplementationEgbert Taylor - ERP Implementation

Taylor get ERP implementation help from Gradient
Egbert Taylor - ERP Implementation

 

The Client

Based in Droitwich Taylor are the world’s leading manufacturer and designer of 4 wheeled, galvanised steel waste and recycling containers and aesthetic street furniture for waste & recycling. Employing 154 people they are UKAS accredited to ISO 9001 (2008) and ISO 14001.

The Problem

Taylor had been working on an ERP implementation of Infor’s CloudSuite for a number of months, with a project team of key users and consultants.  The objective being to replace a disparate range of legacy systems with a single ERP package.

As the planned go live date approached, there was increasing concern about the risk to the business of deploying a system before they were ready.  In addition, the actual cutover process, for a business and internal team new to this type of project, was proving challenging to manage.

The Solution

Due to Gradient’s detailed knowledge of both ERP implementations and the product concerned, we were able to guide the team through the process, taking the system live only one month later.

 

Actions
  • Gradient Consulting spent time understanding the objectives of the project, functional requirements and the current status in terms of testing, training, data and reporting.
  • Test scripts were created, in line with the above, and were worked through with teams from each functional area.
  • Detailed plans were created and a formal cut-over document developed so that all members of the team understood the steps required to take the system live.
  • Trackers were put in place, providing visibility of tasks and progress.
Benefits
  • Taylor were able to commit to the go-live date in the assurance that risks had been mitigated and all activities were planned and scheduled.
  • The internal team were refocused on those tasks that added value to the project.
  • Vendor consultants could be effectively utilised to address piloting issues as they occurred.
  • The business was able to introduce a new ERP product with minimal impact on the business.

What our client says

"On reaching cutover and implementation phase we felt we lacked the knowledge and professionalism to ensure all our pre implementation effort would not be wasted. Gradient and their expertise allowed us to confidently complete the migration without any lost time or problems."

Andrew Davies Finance Director

Case study Case study

Egbert Taylor - ERP Implementation

Taylor had been working on an ERP implementation of Infor’s CloudSuite for a number of months, with a project team of key users and consultants. The objective being to replace a disparate range of legacy systems with a single ERP package. As the planned go live date approached, there was increasing concern..

read more

Case study Case study

Charente - ERP System Selection

Charente (now Harrison Maritime) is a group of companies with a long tradition in the nautical sector. There was a requirement to find an ERP system which would allow them to control three diverse sites across the UK, improve efficiencies and promote further growth.

read more

Case study Case study

Fever-Tree - Spec, Select & Implementation Project

Fever-Tree are a company that have grown rapidly as their premium products have quickly become a huge success in the marketplace.  The company were utilising multiple systems and spreadsheets to manage what was a £100m+ turnover organisation and found that there were silos of information around the business.  They could not easily obtain a single version of the truth or a 360o view of their organisation.

read more

Get in touch with Gradient Consulting to ensure your ERP system is fighting fit.

Call +44 (0) 1282 463710